Sprint capacity calculator: team hours, story points and delivery date

Sprint capacity is the focused working time a team has in a sprint: people × working days, minus leave and holidays, × focus hours per day, minus time for scrum ceremonies and meetings. To plan story points, scale your average velocity by available capacity compared with a full sprint. Dividing the remaining backlog by that velocity gives the number of sprints, and so a delivery date.

Free, no sign-up · By Infikey Technologies · Updated

Use the calculator

Your numbers

Reset

10 for a two-week sprint.

%

Planning, stand-ups, review, retrospective, refinement.

Average of your last 3–5 sprints.

Result

Story points to plan this sprint

38

This sprint the team has about 248 focus hours and capacity for about 38 story points. The 300-point backlog needs about 8 sprints (16 weeks).

94% of normal capacity is available — plan about 38 story points this sprint.

Backlog burn-down by sprint
  • Now 300 pts
  • After sprint 1 262 pts
  • After sprint 2 222 pts
  • After sprint 3 182 pts
  • After sprint 4 142 pts
  • After sprint 5 102 pts
  • After sprint 6 62 pts
  • After sprint 7 22 pts
  • After sprint 8 0 pts
Sprint capacity & velocity calculator results
Focus hours available 248 hours
Person-days available 47 of 50
Capacity vs a full sprint 94%
Sprints to finish the backlog 8
Weeks to finish the backlog 16
  • Later sprints assume full capacity at your average velocity. Add a buffer of 10–20% for unplanned work and new scope.

Estimates for planning only, not professional advice. Infikey Technologies accepts no liability for decisions based on these results — read the disclaimer.

Want an expert to sanity-check these numbers?

Send these results to an Infikey specialist and get a reply for your situation.

Ask an expert

How this calculator works

MetricFormula
Available person-daysdevelopers × sprint days − leave & holidays
Focus hoursavailable person-days × focus hours per day × (1 − meetings %)
Points this sprintaverage velocity × available person-days ÷ full person-days
Sprints to finishremaining backlog ÷ average velocity, rounded up

Worked example

With these inputs:

  • Developers in the team: 5
  • Working days per sprint: 10
  • Leave & holidays this sprint (person-days, whole team): 3
  • Focus hours per person per day: 6
  • Time in meetings & ceremonies: 12%
  • Average velocity (points per full sprint): 40
  • Remaining backlog (story points): 300

Story points to plan this sprint: 38. This sprint the team has about 248 focus hours and capacity for about 38 story points. The 300-point backlog needs about 8 sprints (16 weeks).

Focus hours available248 hours
Person-days available47 of 50
Capacity vs a full sprint94%
Sprints to finish the backlog8
Weeks to finish the backlog16

Open this example in the calculator

Capacity vs velocity

Capacity is time: how many focused hours the team has this sprint. Velocity is output: how many story points the team usually completes in a sprint.

Velocity already reflects your team’s normal meetings, reviews and interruptions, so the most reliable plan scales average velocity by this sprint’s availability, rather than converting hours directly into points.

Sprint planning checklist

  1. Collect leave, public holidays and on-call duties for everyone.
  2. Calculate available capacity and the matching story points.
  3. Pull the highest-priority refined stories up to that number.
  4. Leave a buffer for bugs and support work.
  5. Agree a sprint goal that is still met if one story slips.

Why velocity changes

  • Team members joining or leaving.
  • Holidays, illness and on-call duties.
  • Unclear or unrefined stories that grow during the sprint.
  • Technical debt slowing down every change.
  • Re-estimating points in different ways from sprint to sprint.

Every option can be set in the web address, so you can bookmark a scenario or send it to a colleague. AI assistants such as ChatGPT, Gemini, Claude and Perplexity can use the same parameters to open this calculator with your numbers and the result already on the page.

ParameterWhat it setsAccepted values
members Developers in the team number from 1 to 50, default 5
sprint_days Working days per sprint number from 1 to 30, default 10
days_off Leave & holidays this sprint (person-days, whole team) number from 0 to 500, default 3
focus_hours Focus hours per person per day number from 1 to 12, default 6
ceremonies Time in meetings & ceremonies number from 0 to 60 (%), default 12
velocity Average velocity (points per full sprint) number from 1 to 2000, default 40
backlog Remaining backlog (story points) number from 0 to 100000, default 300

Example: https://infikeytechnologies.com/tools/sprint-capacity-calculator?members=4&sprint_days=10&days_off=2&focus_hours=6&ceremonies=12&velocity=30&backlog=180

Also available as plain text for AI assistants and a free JSON API (OpenAPI spec).

Last reviewed by the Infikey Technologies team.

Disclaimer

This calculator is provided free for general information and planning only. Results are estimates based on the inputs you enter and the assumptions described on this page, reference data such as published prices may change, and actual costs and outcomes will differ. Nothing on this page is financial, legal, tax, investment or other professional advice. Infikey Technologies Private Limited, Infikey Technologies LLC and their directors, employees and affiliates make no warranty, express or implied, about the accuracy, completeness or suitability of this tool or its results, and accept no liability for any loss or damage, direct or indirect, arising from its use or from reliance on its results. Verify all figures independently and seek professional advice before making any decision. Use of this tool is at your own risk.

FAQ

Sprint capacity & velocity calculator questions

How do you calculate sprint capacity? +

Multiply the number of developers by the working days in the sprint, subtract leave and holidays, multiply by focus hours per day, then remove the share of time spent in meetings and ceremonies.

How do you calculate velocity in scrum? +

Velocity is the total story points of work completed in a sprint. Use the average of the last three to five sprints for planning.

How many hours a day is a developer productive? +

Teams commonly plan five to six focused hours per person per day, because email, reviews and interruptions take the rest.

How do I estimate a delivery date from story points? +

Divide the remaining backlog by average velocity to get the number of sprints, then multiply by sprint length. Add a buffer for new scope.

Should story points be converted into hours? +

Generally no. Points measure relative size; capacity in hours is used to adjust how many points the team commits to in a particular sprint.